Councillors deferred the Dulwich Leisure Centre heat pump plans on 10 November so revisions can be considered. No new date is set, and the grant runs out in March.

Councillors have put off a decision on six heat pumps for the roof of Dulwich Leisure Centre. Southwark’s Planning Committee (Smaller Applications) deferred both applications on Tuesday 10 November, without discussing them.

The reason given was “to allow further consideration of revisions to the proposed scheme”. The chair, Councillor Richard Taylor, moved the deferral at the start of the item. Members voted by a show of hands and he called the vote unanimous. The whole item took under two minutes, the council’s recording of the meeting shows.

Planning officers had recommended approval, despite 59 objections from about 32 addresses and none in support. The chair told the meeting that members had already been told a deferral would be proposed.

What was deferred

The two applications are:

  • 26/AP/0390, planning permission for the heat pumps, an acoustic enclosure, an electricity substation, a dropped kerb on Crystal Palace Road, moved cycle parking and new timber windows in the pool and gym halls
  • 26/AP/0391, listed building consent for the same works on the Grade II listed former Dulwich Public Baths

Both still read “Awaiting decision” on the council’s planning register when we checked on 15 November. The council has not published what the revisions are.

Why the timing matters

The heat pumps would replace the centre’s gas boilers. They are part of a £12.1m programme to take five council leisure centres off gas. Of that, £9.5m is a government Public Sector Decarbonisation Scheme grant.

The council’s own report says the grant “must be fully drawn down by 31 March 2027”. A council report in August named Dulwich and Camberwell as “the final projects to be delivered”. Camberwell’s works contract was awarded on 29 September. Dulwich has neither planning permission nor a works contract, and its agreed decision date of 14 October had passed before Tuesday’s meeting.

The same committee next meets on 7 December, then on 20 January, the council’s meetings calendar shows. The council has not said whether the scheme will be on either agenda.

What it means for you

  • If you objected, nothing has been decided. The council consulted neighbours three times on earlier changes to this scheme, the officer report says. Watch the planning register for new drawings or a fresh noise report.
  • If you want to speak when it returns, the council’s procedure note says to register with the constitutional team by 5pm on the working day before the meeting.
  • If you swim or train at Dulwich, nothing changes. With no permission and no contractor, no works or closures are planned yet.

The noise studies, the pump schedule and the officers’ reasoning are in our preview of the meeting and our first report on the objections.